Schlegel Enterprises, INC.
UEI QYNLTNS4HTN1 · MT · SAM.gov record ↗
Obligations by agency
- Department Of Agriculture$1.8M
Obligations by NAICS
Monthly obligations
Contracts ending within 18 months (recompete watch)
- 1240LU25C0040 ↗$31K
THE CONTRACT CONSISTS OF PROCUREMENT, DELIVERY, SITE PREPARATION, AND INSTILLATION IN ACCORDANCE WITH THE MANUFACTURERS, SPECIFICATIONS FOR ONE NEW CONCRETE VAULT TOILET AT THE STAKED LOCATION ON USFS ROAD 15061. THIS CONTRACT REQUIRES FURNISHING LAB
- Ends
- Nov 29, 2026
- Started
- Sep 24, 2025
- Agency
- Forest Service
- NAICS
- 238910
- 1240LU26F0086 ↗$162K
8 MILE CREEK BRIDGE REPLACEMENT
- Ends
- Aug 31, 2027
- Started
- May 2, 2027
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0073 ↗$131K
THIS PROJECT WILL IMPROVE THE ANTELOPE BASIN ROAD (230) ON THE MADISON RANGER DISTRICT OF THE BEAVERHEAD DEERLODGE NATIONAL FOREST.
- Ends
- Sep 29, 2027
- Started
- Jun 14, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0046 ↗$45K
SPECIFIC IMPROVEMENTS TO FOREST ROAD 267, M.P. 2.257 INCLUDE, BUT ARE NOT LIMITED TO: REMOVAL AND DISPOSAL OF TWO EXISTING CSP CULVERTS AND INSTALLATION OF A NEW CORRUGATED STEEL PIPE-ARCH CULVERT, STRUCTURE EXCAVATION/BACKFILL, SURFACING, STRUCTURE
- Ends
- Sep 30, 2027
- Started
- Apr 26, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0010 ↗$146K
SPECIFIC IMPROVEMENTS TO FSR 267, INCLUDE, BUT ARE NOT LIMITED TO: SELECTIVE CLEARING, REMOVAL AND DISPOSAL OF EXISTING CSP CULVERTS, INSTALLATION OF NEW CSP CULVERTS, CONSTRUCTION OF NEW DRIVABLE DIPS, SHOULDER STABILIZATION USING CLASS 3 RIPRAP, AG
- Ends
- Sep 30, 2027
- Started
- Feb 8, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0082 ↗$85K
GLACIER CREEK BRIDGE RIPRAP
- Ends
- Oct 14, 2027
- Started
- Jul 23, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0072 ↗$220K
CHIEF JOSEPH TRAILHEAD IMPROVEMENTS, BEAVERHEAD DEERLODGE NATIONAL FOREST
- Ends
- Oct 14, 2027
- Started
- May 31, 2027
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0058 ↗$437K
TASK ORDER FOR DOUBLE BARRELL & SQUARE PEG ROAD CONSTRUCTION ON THE FLATHEAD NATIONAL FOREST CONSTRUCTING ROADS ON THE LOST CREEK DIVIDE IN SUPPORT OF THE DOUBLE BARREL TIMBER SALE.
- Ends
- Oct 28, 2027
- Started
- May 31, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0076 ↗$85K
REMOVAL OF 60" CORRUGATED STEEL PIPE AND REPLACEMENT WITH 96" CORRUGATED STEEL PIPE ON NFSR 368 AT THE NORTH FORK OF DEEP CREEK CROSSING.
- Ends
- Oct 30, 2027
- Started
- Jul 21, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0080 ↗$274K
CONSTRUCT TWO NEW AQUATIC ORGANISM PASSAGEWAYS AOPS IN THE PLANT CREEK DRAINAGE ON THE MISSOULA DISTRICT OF THE LOLO NATIONAL FOREST. ONE ON NFSR 464 AT MP 0.272, AND ONE ON NFSR 19022 AT MP 0.000. THE NEW STRUCTURES WILL REPLACE STORMED DAMAGED UNSU
- Ends
- Dec 30, 2027
- Started
- Jul 15, 2026
- Agency
- Forest Service
- NAICS
- 237310
| PIID | Description | Agency | NAICS | Obligated | Start | End |
|---|---|---|---|---|---|---|
| 1240LU25C0040 ↗ | THE CONTRACT CONSISTS OF PROCUREMENT, DELIVERY, SITE PREPARATION, AND INSTILLATION IN ACCORDANCE WITH THE MANUFACTURERS, SPECIFICATIONS FOR ONE NEW CONCRETE VAULT TOILET AT THE STAKED LOCATION ON USFS ROAD 15061. THIS CONTRACT REQUIRES FURNISHING LAB | Forest Service | 238910 | $31K | Sep 24, 2025 | Nov 29, 2026 |
| 1240LU26F0086 ↗ | 8 MILE CREEK BRIDGE REPLACEMENT | Forest Service | 237310 | $162K | May 2, 2027 | Aug 31, 2027 |
| 1240LU26F0073 ↗ | THIS PROJECT WILL IMPROVE THE ANTELOPE BASIN ROAD (230) ON THE MADISON RANGER DISTRICT OF THE BEAVERHEAD DEERLODGE NATIONAL FOREST. | Forest Service | 237310 | $131K | Jun 14, 2026 | Sep 29, 2027 |
| 1240LU26F0046 ↗ | SPECIFIC IMPROVEMENTS TO FOREST ROAD 267, M.P. 2.257 INCLUDE, BUT ARE NOT LIMITED TO: REMOVAL AND DISPOSAL OF TWO EXISTING CSP CULVERTS AND INSTALLATION OF A NEW CORRUGATED STEEL PIPE-ARCH CULVERT, STRUCTURE EXCAVATION/BACKFILL, SURFACING, STRUCTURE | Forest Service | 237310 | $45K | Apr 26, 2026 | Sep 30, 2027 |
| 1240LU26F0010 ↗ | SPECIFIC IMPROVEMENTS TO FSR 267, INCLUDE, BUT ARE NOT LIMITED TO: SELECTIVE CLEARING, REMOVAL AND DISPOSAL OF EXISTING CSP CULVERTS, INSTALLATION OF NEW CSP CULVERTS, CONSTRUCTION OF NEW DRIVABLE DIPS, SHOULDER STABILIZATION USING CLASS 3 RIPRAP, AG | Forest Service | 237310 | $146K | Feb 8, 2026 | Sep 30, 2027 |
| 1240LU26F0082 ↗ | GLACIER CREEK BRIDGE RIPRAP | Forest Service | 237310 | $85K | Jul 23, 2026 | Oct 14, 2027 |
| 1240LU26F0072 ↗ | CHIEF JOSEPH TRAILHEAD IMPROVEMENTS, BEAVERHEAD DEERLODGE NATIONAL FOREST | Forest Service | 237310 | $220K | May 31, 2027 | Oct 14, 2027 |
| 1240LU26F0058 ↗ | TASK ORDER FOR DOUBLE BARRELL & SQUARE PEG ROAD CONSTRUCTION ON THE FLATHEAD NATIONAL FOREST CONSTRUCTING ROADS ON THE LOST CREEK DIVIDE IN SUPPORT OF THE DOUBLE BARREL TIMBER SALE. | Forest Service | 237310 | $437K | May 31, 2026 | Oct 28, 2027 |
| 1240LU26F0076 ↗ | REMOVAL OF 60" CORRUGATED STEEL PIPE AND REPLACEMENT WITH 96" CORRUGATED STEEL PIPE ON NFSR 368 AT THE NORTH FORK OF DEEP CREEK CROSSING. | Forest Service | 237310 | $85K | Jul 21, 2026 | Oct 30, 2027 |
| 1240LU26F0080 ↗ | CONSTRUCT TWO NEW AQUATIC ORGANISM PASSAGEWAYS AOPS IN THE PLANT CREEK DRAINAGE ON THE MISSOULA DISTRICT OF THE LOLO NATIONAL FOREST. ONE ON NFSR 464 AT MP 0.272, AND ONE ON NFSR 19022 AT MP 0.000. THE NEW STRUCTURES WILL REPLACE STORMED DAMAGED UNSU | Forest Service | 237310 | $274K | Jul 15, 2026 | Dec 30, 2027 |
Largest awards
- 1240LU26F0058 ↗$437K
TASK ORDER FOR DOUBLE BARRELL & SQUARE PEG ROAD CONSTRUCTION ON THE FLATHEAD NATIONAL FOREST CONSTRUCTING ROADS ON THE LOST CREEK DIVIDE IN SUPPORT OF THE DOUBLE BARREL TIMBER SALE.
- Ends
- Oct 28, 2027
- Started
- May 31, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0080 ↗$274K
CONSTRUCT TWO NEW AQUATIC ORGANISM PASSAGEWAYS AOPS IN THE PLANT CREEK DRAINAGE ON THE MISSOULA DISTRICT OF THE LOLO NATIONAL FOREST. ONE ON NFSR 464 AT MP 0.272, AND ONE ON NFSR 19022 AT MP 0.000. THE NEW STRUCTURES WILL REPLACE STORMED DAMAGED UNSU
- Ends
- Dec 30, 2027
- Started
- Jul 15, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0072 ↗$220K
CHIEF JOSEPH TRAILHEAD IMPROVEMENTS, BEAVERHEAD DEERLODGE NATIONAL FOREST
- Ends
- Oct 14, 2027
- Started
- May 31, 2027
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0086 ↗$162K
8 MILE CREEK BRIDGE REPLACEMENT
- Ends
- Aug 31, 2027
- Started
- May 2, 2027
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0010 ↗$146K
SPECIFIC IMPROVEMENTS TO FSR 267, INCLUDE, BUT ARE NOT LIMITED TO: SELECTIVE CLEARING, REMOVAL AND DISPOSAL OF EXISTING CSP CULVERTS, INSTALLATION OF NEW CSP CULVERTS, CONSTRUCTION OF NEW DRIVABLE DIPS, SHOULDER STABILIZATION USING CLASS 3 RIPRAP, AG
- Ends
- Sep 30, 2027
- Started
- Feb 8, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0073 ↗$131K
THIS PROJECT WILL IMPROVE THE ANTELOPE BASIN ROAD (230) ON THE MADISON RANGER DISTRICT OF THE BEAVERHEAD DEERLODGE NATIONAL FOREST.
- Ends
- Sep 29, 2027
- Started
- Jun 14, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1284LM25P0022 ↗$95K
ROAD MAINTENANCE BLADING ON THE NINEMILE AND SEELEY RANGER DISTRICTS FOR 2025
- Ends
- Nov 14, 2025
- Started
- Jun 29, 2025
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0076 ↗$85K
REMOVAL OF 60" CORRUGATED STEEL PIPE AND REPLACEMENT WITH 96" CORRUGATED STEEL PIPE ON NFSR 368 AT THE NORTH FORK OF DEEP CREEK CROSSING.
- Ends
- Oct 30, 2027
- Started
- Jul 21, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0082 ↗$85K
GLACIER CREEK BRIDGE RIPRAP
- Ends
- Oct 14, 2027
- Started
- Jul 23, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU25F0076 ↗$46K
INSTALL ARCH PIPE ON USFS RD 1900 MILE POST (MP) 1.80 CROSSING BEETLE CREEK. THE ORIGINAL PIPE IS REMOVED, AND THE ROAD IS TRENCHED TO ALLOW PASSAGE OF THE STREAM.
- Ends
- Oct 22, 2026
- Started
- Aug 31, 2025
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0046 ↗$45K
SPECIFIC IMPROVEMENTS TO FOREST ROAD 267, M.P. 2.257 INCLUDE, BUT ARE NOT LIMITED TO: REMOVAL AND DISPOSAL OF TWO EXISTING CSP CULVERTS AND INSTALLATION OF A NEW CORRUGATED STEEL PIPE-ARCH CULVERT, STRUCTURE EXCAVATION/BACKFILL, SURFACING, STRUCTURE
- Ends
- Sep 30, 2027
- Started
- Apr 26, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU26F0070 ↗$35K
INSTALL BRIDGE RUNNING PLANKS ON 8 BRIDGES ACROSS THE HELENA - LEWIS & CLARK NATIONAL FOREST.
- Ends
- Sep 29, 2026
- Started
- Jun 17, 2026
- Agency
- Forest Service
- NAICS
- 237310
- 1240LU25C0040 ↗$31K
THE CONTRACT CONSISTS OF PROCUREMENT, DELIVERY, SITE PREPARATION, AND INSTILLATION IN ACCORDANCE WITH THE MANUFACTURERS, SPECIFICATIONS FOR ONE NEW CONCRETE VAULT TOILET AT THE STAKED LOCATION ON USFS ROAD 15061. THIS CONTRACT REQUIRES FURNISHING LAB
- Ends
- Nov 29, 2026
- Started
- Sep 24, 2025
- Agency
- Forest Service
- NAICS
- 238910
- 1240LQ26F0016 ↗$500
EFFICIENT CONTRACT VEHICLE TO ACCOMPLISH ROAD MAINTENANCE IN REGION 1 GUARANTEE MINIMUM
- Ends
- Sep 28, 2026
- Started
- Dec 14, 2025
- Agency
- Forest Service
- NAICS
- 237310
USFS, REGION 1, ROAD AND BRIDGE CONSTRUCTION MATOC
- Ends
- —
- Started
- Dec 15, 2024
- Agency
- Forest Service
- NAICS
- 237310
GAOA LOGGING CREEK CAMPGROUND UPDATES HLCNF
- Ends
- Sep 4, 2025
- Started
- Jul 4, 2025
- Agency
- Forest Service
- NAICS
- 237310
SKID CREEK CULVERT REPLACEMENT KOOTENAI NF
- Ends
- Sep 29, 2025
- Started
- Jun 30, 2025
- Agency
- Forest Service
- NAICS
- 237310
ALICE CREEK ROAD REROUTE
- Ends
- Sep 29, 2025
- Started
- Aug 25, 2024
- Agency
- Forest Service
- NAICS
- 237310
THE PROJECT CONSISTS OF NEW ROAD CONSTRUCTION, EXISTING ROAD RECONSTRUCTION, DRAINAGE FEATURE INSTALLATION, CATTLEGUARD AND GATE INSTALLATION AND POSSIBLE GRAVEL SURFACING PLACEMENT.
- Ends
- Sep 30, 2025
- Started
- May 31, 2024
- Agency
- Forest Service
- NAICS
- 237310
GAOA TIGER CREEK BRIDGE REPLACEMENT AND DETOUR FLATHEAD NF
- Ends
- Oct 29, 2025
- Started
- May 31, 2025
- Agency
- Forest Service
- NAICS
- 237310
GAOA BACKCOUNTRY AIRSTRIP ROAD MAINTENANCE FLATHEAD NF
- Ends
- Oct 30, 2025
- Started
- May 31, 2025
- Agency
- Forest Service
- NAICS
- 237310
MOD 0001 TO GAOA - HUNGRY HORSE CREEK AOP & DETOUR TASK ORDER IS A TIME EXTENSION WITHIN SCOPE TO COMPLETE THE FINAL 10% OF THE PROJECT. EARLY WINTER STORM MADE IT DIFFICULT TO FINISH ON TIME THEREFORE A NEW PERIOD ENDING DATE WILL BE 06/15/2025
- Ends
- Jun 14, 2026
- Started
- Jul 31, 2024
- Agency
- Forest Service
- NAICS
- 237310
GAOA TALLY LAKE REC SITE ROADS DEFERRED MAINTENANCE FLATHEAD NATIONAL FOREST
- Ends
- Jul 24, 2025
- Started
- Apr 14, 2025
- Agency
- Forest Service
- NAICS
- 237310
MISCELLANEOUS HEAVY EQUIPMENT FOR EAST ZONE, REGIONS 1, 2 AND 4
- Ends
- —
- Started
- Feb 5, 2026
- Agency
- Forest Service
- NAICS
- 115310
HEAVY EQUIPMENT FOR EAST ZONE (REGIONS 1, 2, 4, AND 9)
- Ends
- —
- Started
- Feb 5, 2026
- Agency
- Forest Service
- NAICS
- 115310
| PIID | Description | Agency | NAICS | Obligated | Start | End |
|---|---|---|---|---|---|---|
| 1240LU26F0058 ↗ | TASK ORDER FOR DOUBLE BARRELL & SQUARE PEG ROAD CONSTRUCTION ON THE FLATHEAD NATIONAL FOREST CONSTRUCTING ROADS ON THE LOST CREEK DIVIDE IN SUPPORT OF THE DOUBLE BARREL TIMBER SALE. | Forest Service | 237310 | $437K | May 31, 2026 | Oct 28, 2027 |
| 1240LU26F0080 ↗ | CONSTRUCT TWO NEW AQUATIC ORGANISM PASSAGEWAYS AOPS IN THE PLANT CREEK DRAINAGE ON THE MISSOULA DISTRICT OF THE LOLO NATIONAL FOREST. ONE ON NFSR 464 AT MP 0.272, AND ONE ON NFSR 19022 AT MP 0.000. THE NEW STRUCTURES WILL REPLACE STORMED DAMAGED UNSU | Forest Service | 237310 | $274K | Jul 15, 2026 | Dec 30, 2027 |
| 1240LU26F0072 ↗ | CHIEF JOSEPH TRAILHEAD IMPROVEMENTS, BEAVERHEAD DEERLODGE NATIONAL FOREST | Forest Service | 237310 | $220K | May 31, 2027 | Oct 14, 2027 |
| 1240LU26F0086 ↗ | 8 MILE CREEK BRIDGE REPLACEMENT | Forest Service | 237310 | $162K | May 2, 2027 | Aug 31, 2027 |
| 1240LU26F0010 ↗ | SPECIFIC IMPROVEMENTS TO FSR 267, INCLUDE, BUT ARE NOT LIMITED TO: SELECTIVE CLEARING, REMOVAL AND DISPOSAL OF EXISTING CSP CULVERTS, INSTALLATION OF NEW CSP CULVERTS, CONSTRUCTION OF NEW DRIVABLE DIPS, SHOULDER STABILIZATION USING CLASS 3 RIPRAP, AG | Forest Service | 237310 | $146K | Feb 8, 2026 | Sep 30, 2027 |
| 1240LU26F0073 ↗ | THIS PROJECT WILL IMPROVE THE ANTELOPE BASIN ROAD (230) ON THE MADISON RANGER DISTRICT OF THE BEAVERHEAD DEERLODGE NATIONAL FOREST. | Forest Service | 237310 | $131K | Jun 14, 2026 | Sep 29, 2027 |
| 1284LM25P0022 ↗ | ROAD MAINTENANCE BLADING ON THE NINEMILE AND SEELEY RANGER DISTRICTS FOR 2025 | Forest Service | 237310 | $95K | Jun 29, 2025 | Nov 14, 2025 |
| 1240LU26F0076 ↗ | REMOVAL OF 60" CORRUGATED STEEL PIPE AND REPLACEMENT WITH 96" CORRUGATED STEEL PIPE ON NFSR 368 AT THE NORTH FORK OF DEEP CREEK CROSSING. | Forest Service | 237310 | $85K | Jul 21, 2026 | Oct 30, 2027 |
| 1240LU26F0082 ↗ | GLACIER CREEK BRIDGE RIPRAP | Forest Service | 237310 | $85K | Jul 23, 2026 | Oct 14, 2027 |
| 1240LU25F0076 ↗ | INSTALL ARCH PIPE ON USFS RD 1900 MILE POST (MP) 1.80 CROSSING BEETLE CREEK. THE ORIGINAL PIPE IS REMOVED, AND THE ROAD IS TRENCHED TO ALLOW PASSAGE OF THE STREAM. | Forest Service | 237310 | $46K | Aug 31, 2025 | Oct 22, 2026 |
| 1240LU26F0046 ↗ | SPECIFIC IMPROVEMENTS TO FOREST ROAD 267, M.P. 2.257 INCLUDE, BUT ARE NOT LIMITED TO: REMOVAL AND DISPOSAL OF TWO EXISTING CSP CULVERTS AND INSTALLATION OF A NEW CORRUGATED STEEL PIPE-ARCH CULVERT, STRUCTURE EXCAVATION/BACKFILL, SURFACING, STRUCTURE | Forest Service | 237310 | $45K | Apr 26, 2026 | Sep 30, 2027 |
| 1240LU26F0070 ↗ | INSTALL BRIDGE RUNNING PLANKS ON 8 BRIDGES ACROSS THE HELENA - LEWIS & CLARK NATIONAL FOREST. | Forest Service | 237310 | $35K | Jun 17, 2026 | Sep 29, 2026 |
| 1240LU25C0040 ↗ | THE CONTRACT CONSISTS OF PROCUREMENT, DELIVERY, SITE PREPARATION, AND INSTILLATION IN ACCORDANCE WITH THE MANUFACTURERS, SPECIFICATIONS FOR ONE NEW CONCRETE VAULT TOILET AT THE STAKED LOCATION ON USFS ROAD 15061. THIS CONTRACT REQUIRES FURNISHING LAB | Forest Service | 238910 | $31K | Sep 24, 2025 | Nov 29, 2026 |
| 1240LQ26F0016 ↗ | EFFICIENT CONTRACT VEHICLE TO ACCOMPLISH ROAD MAINTENANCE IN REGION 1 GUARANTEE MINIMUM | Forest Service | 237310 | $500 | Dec 14, 2025 | Sep 28, 2026 |
| 1240LU25D0018 ↗ | USFS, REGION 1, ROAD AND BRIDGE CONSTRUCTION MATOC | Forest Service | 237310 | $0 | Dec 15, 2024 | — |
| 1240LU24F0008 ↗ | GAOA LOGGING CREEK CAMPGROUND UPDATES HLCNF | Forest Service | 237310 | $0 | Jul 4, 2025 | Sep 4, 2025 |
| 1240LU24F0070 ↗ | SKID CREEK CULVERT REPLACEMENT KOOTENAI NF | Forest Service | 237310 | $0 | Jun 30, 2025 | Sep 29, 2025 |
| 1240LU24F0061 ↗ | ALICE CREEK ROAD REROUTE | Forest Service | 237310 | $0 | Aug 25, 2024 | Sep 29, 2025 |
| 1240LU24F0010 ↗ | THE PROJECT CONSISTS OF NEW ROAD CONSTRUCTION, EXISTING ROAD RECONSTRUCTION, DRAINAGE FEATURE INSTALLATION, CATTLEGUARD AND GATE INSTALLATION AND POSSIBLE GRAVEL SURFACING PLACEMENT. | Forest Service | 237310 | $0 | May 31, 2024 | Sep 30, 2025 |
| 1240LU24F0072 ↗ | GAOA TIGER CREEK BRIDGE REPLACEMENT AND DETOUR FLATHEAD NF | Forest Service | 237310 | $0 | May 31, 2025 | Oct 29, 2025 |
| 1240LU24F0068 ↗ | GAOA BACKCOUNTRY AIRSTRIP ROAD MAINTENANCE FLATHEAD NF | Forest Service | 237310 | $0 | May 31, 2025 | Oct 30, 2025 |
| 1240LU24F0050 ↗ | MOD 0001 TO GAOA - HUNGRY HORSE CREEK AOP & DETOUR TASK ORDER IS A TIME EXTENSION WITHIN SCOPE TO COMPLETE THE FINAL 10% OF THE PROJECT. EARLY WINTER STORM MADE IT DIFFICULT TO FINISH ON TIME THEREFORE A NEW PERIOD ENDING DATE WILL BE 06/15/2025 | Forest Service | 237310 | $0 | Jul 31, 2024 | Jun 14, 2026 |
| 1240LU24F0060 ↗ | GAOA TALLY LAKE REC SITE ROADS DEFERRED MAINTENANCE FLATHEAD NATIONAL FOREST | Forest Service | 237310 | $0 | Apr 14, 2025 | Jul 24, 2025 |
| 1202SB26T8014 ↗ | MISCELLANEOUS HEAVY EQUIPMENT FOR EAST ZONE, REGIONS 1, 2 AND 4 | Forest Service | 115310 | $0 | Feb 5, 2026 | — |
| 1202SB26T8900 ↗ | HEAVY EQUIPMENT FOR EAST ZONE (REGIONS 1, 2, 4, AND 9) | Forest Service | 115310 | $0 | Feb 5, 2026 | — |