FedQuery

Sealevel Construction INC

UEI SMXLMJXRH5M7 · LA · SAM.gov record ↗

$12.5M
FY2025 obligations
5
Contract awards
Mar 31, 2023
First action
Sep 29, 2025
Latest action

Obligations by agency

  • Department Of Defense$12.5M

Obligations by NAICS

Monthly obligations

Oct 24
Dec 24
Feb 25
Jul 25
Aug 25
Sep 25

Contracts ending within 18 months (recompete watch)

PIIDDescriptionAgencyNAICSObligatedStartEnd
W912EE23C0005STRUT ARM AND GIRDER ANODE CHANGES CONTRACT FOR LOCK & DAM NO. 1 (BOGGS) TAINTER GATE REPLACEMENT, RED RIVER BASIN, CATAHOULA PARISH, LOUISIANA AT CATAHOULA PARISH. REFERENCE NO. R00005 V0002 STRUT ARM AND GIRDER ANODE CHANGESDepartment Of The Army237990$184KMar 31, 2023Nov 21, 2026
W912EK25CA017THE WORK INCLUDES, BUT IS NOT LIMITED TO, THE FABRICATION, ASSEMBLY, PAINTING, AND DELIVERY OF A STEEL BULKHEADDepartment Of The Army332312$1.3MSep 30, 2025Mar 29, 2027

Largest awards

PIIDDescriptionAgencyNAICSObligatedStartEnd
W912P825C0031CALCASIEU RIVER SALTWATER BARRIER SECTOR GATE FABRICATIONDepartment Of The Army332312$6.1MOct 7, 2025Mar 27, 2028
W912EK25C0018LOCK & DAM 21 TAINTER GATE FABDepartment Of The Army332312$4.9MOct 1, 2025Jan 13, 2029
W912EK25CA017THE WORK INCLUDES, BUT IS NOT LIMITED TO, THE FABRICATION, ASSEMBLY, PAINTING, AND DELIVERY OF A STEEL BULKHEADDepartment Of The Army332312$1.3MSep 30, 2025Mar 29, 2027
W912EE23C0005STRUT ARM AND GIRDER ANODE CHANGES CONTRACT FOR LOCK & DAM NO. 1 (BOGGS) TAINTER GATE REPLACEMENT, RED RIVER BASIN, CATAHOULA PARISH, LOUISIANA AT CATAHOULA PARISH. REFERENCE NO. R00005 V0002 STRUT ARM AND GIRDER ANODE CHANGESDepartment Of The Army237990$184KMar 31, 2023Nov 21, 2026
W912EK24C0039THE REASON FOR THIS MODIFICATION IS TO ESTABLISH THE CONTRACT COMPLETION DATE AND UPDATE SPECIFICATION SECTION 00 73 05.Department Of The Army332312$-61KSep 26, 2024Apr 8, 2026