Veolia Water West Operating Services INC
UEI VQTPF9KTZAY8 · MA · SAM.gov record ↗
Obligations by agency
- Department Of State$66.1M
Obligations by NAICS
Monthly obligations
Contracts ending within 18 months (recompete watch)
- 191BWC26C0043 ↗$16.5M
---------- COMMENTS: THE SBIWTP IS A 25 MILLION GALLON PER DAY WASTEWATER TREATMENT PLANT THAT TREATS WASTEWATER ORIGINATING FROM TIJUANA, BAJA CALIFORNIA, MEXICO. THE TREATMENT SYSTEM INCLUDES AUXILIARY FACILITIES SUCH AS THE CANYON COLLECTION SYST
- Ends
- Mar 30, 2027
- Started
- Mar 31, 2026
- Agency
- International Boundary And Water Commission: U.S.-Mexico
- NAICS
- 221320
| PIID | Description | Agency | NAICS | Obligated | Start | End |
|---|---|---|---|---|---|---|
| 191BWC26C0043 ↗ | ---------- COMMENTS: THE SBIWTP IS A 25 MILLION GALLON PER DAY WASTEWATER TREATMENT PLANT THAT TREATS WASTEWATER ORIGINATING FROM TIJUANA, BAJA CALIFORNIA, MEXICO. THE TREATMENT SYSTEM INCLUDES AUXILIARY FACILITIES SUCH AS THE CANYON COLLECTION SYST | International Boundary And Water Commission: U.S.-Mexico | 221320 | $16.5M | Mar 31, 2026 | Mar 30, 2027 |
Largest awards
- 191BWC20C0003 ↗$38.7M
FUNDING OPTION YEAR FOUR THROUGH CR
- Ends
- Mar 30, 2026
- Started
- Sep 27, 2020
- Agency
- International Boundary And Water Commission: U.S.-Mexico
- NAICS
- 221320
- 191BWC26C0043 ↗$16.5M
---------- COMMENTS: THE SBIWTP IS A 25 MILLION GALLON PER DAY WASTEWATER TREATMENT PLANT THAT TREATS WASTEWATER ORIGINATING FROM TIJUANA, BAJA CALIFORNIA, MEXICO. THE TREATMENT SYSTEM INCLUDES AUXILIARY FACILITIES SUCH AS THE CANYON COLLECTION SYST
- Ends
- Mar 30, 2027
- Started
- Mar 31, 2026
- Agency
- International Boundary And Water Commission: U.S.-Mexico
- NAICS
- 221320
- 191BWC24C0006 ↗$8.6M
ADDITIONAL WORK OUTSIDE THE SCOPE BUT CRITICAL TO THE REHABILITATION OF BELT FILTER PRESS.
- Ends
- Aug 22, 2026
- Started
- May 16, 2025
- Agency
- International Boundary And Water Commission: U.S.-Mexico
- NAICS
- 221320
- 191BWC23C0018 ↗$1.5M
FORTY (40) ADDITIONAL PLUG VALVES ON USST 1 & 2, WHICH ARE ESSENTIAL FOR MAINTAINING ADEQUATE ISOLATION CAPABILITIES AND FULFILLING OPERATIONAL REQUIREMENTS FOR TANK SWITCHING DURING PROCESS CONTROL OPERATIONS. INCORPORATES PROVISIONS FOR CLEANING
- Ends
- Apr 29, 2026
- Started
- Sep 29, 2023
- Agency
- International Boundary And Water Commission: U.S.-Mexico
- NAICS
- 221320
- 191BWC23C0009 ↗$885K
GATES 3 AND 4 ELECTRICAL UPGRADESJB-1 REHABILITATION CHANGE ORDER-2
- Ends
- Jun 15, 2026
- Started
- Aug 9, 2023
- Agency
- International Boundary And Water Commission: U.S.-Mexico
- NAICS
- 221320
| PIID | Description | Agency | NAICS | Obligated | Start | End |
|---|---|---|---|---|---|---|
| 191BWC20C0003 ↗ | FUNDING OPTION YEAR FOUR THROUGH CR | International Boundary And Water Commission: U.S.-Mexico | 221320 | $38.7M | Sep 27, 2020 | Mar 30, 2026 |
| 191BWC26C0043 ↗ | ---------- COMMENTS: THE SBIWTP IS A 25 MILLION GALLON PER DAY WASTEWATER TREATMENT PLANT THAT TREATS WASTEWATER ORIGINATING FROM TIJUANA, BAJA CALIFORNIA, MEXICO. THE TREATMENT SYSTEM INCLUDES AUXILIARY FACILITIES SUCH AS THE CANYON COLLECTION SYST | International Boundary And Water Commission: U.S.-Mexico | 221320 | $16.5M | Mar 31, 2026 | Mar 30, 2027 |
| 191BWC24C0006 ↗ | ADDITIONAL WORK OUTSIDE THE SCOPE BUT CRITICAL TO THE REHABILITATION OF BELT FILTER PRESS. | International Boundary And Water Commission: U.S.-Mexico | 221320 | $8.6M | May 16, 2025 | Aug 22, 2026 |
| 191BWC23C0018 ↗ | FORTY (40) ADDITIONAL PLUG VALVES ON USST 1 & 2, WHICH ARE ESSENTIAL FOR MAINTAINING ADEQUATE ISOLATION CAPABILITIES AND FULFILLING OPERATIONAL REQUIREMENTS FOR TANK SWITCHING DURING PROCESS CONTROL OPERATIONS. INCORPORATES PROVISIONS FOR CLEANING | International Boundary And Water Commission: U.S.-Mexico | 221320 | $1.5M | Sep 29, 2023 | Apr 29, 2026 |
| 191BWC23C0009 ↗ | GATES 3 AND 4 ELECTRICAL UPGRADESJB-1 REHABILITATION CHANGE ORDER-2 | International Boundary And Water Commission: U.S.-Mexico | 221320 | $885K | Aug 9, 2023 | Jun 15, 2026 |