FedQuery
ActiveCombined Synopsis/SolicitationSmall Business Set Aside - Total

Fire suppression system installation

AGRICULTURE, DEPARTMENT OF › ANIMAL AND PLANT HEALTH INSPECTION SERVICE › MRPBS MINNEAPOLIS MN

Solicitation #
12639526Q0210
Posted
Sep 10, 2026
Response deadline
Sep 11, 2026
Archive date
Sep 29, 2026
NAICS
PSC
Y1JZ
Place of performance
Edinburg, TX, 78541
Contact
Jim Roloff · [email protected]

Description

Due to a recent fire in building 6418 at Moore Air Base, Texas, a wet fire suppression system is needed. Building 6418 was constructed in the early 1980s with no fire suppression initially. Contractor shall provide design/as-built drawings submittals and installation of a new retrofitted system. The system shall be a turnkey project encompassing everything needed to have a fully functioning fire suppression system. Solicitation documents are posted below.

NOTE: For those wishing to attend the site visit, please send names of attendees to james.g.roloff@usda,gov. A valid drivers license or state ID is required. Amendment 1 is posted below.

RFI: Does Building 6418 currently have an existing fire alarm panel/system that the sprinkler monitoring would tie into? If so, could you please provide the panel/system type, make/model, or any available details needed for a sprinkler monitoring quote? The fire panels are old and obsolete. They will be replaced at another time, but the new sprinkler system must be able to connect to a fire panel in the future. No monitoring is needed. The sign-in sheet for the site visit is posted below. Building drawings posted below. RFIs and responses posted below. Amendment 2 is posted below. It extends the closing date. Amendment 3 is posted below. It extends the closing date. Additional RFIs and responses posted below. Amendment 4 is posted below. There's a change to the response to RFI 6 posted here on August 17. The correct answer is as follows: 6) Please confirm if a CVPC/PEX fire suppression would be sufficient or the USDA prefers schedule 10 or schedule 40 Victaulic black iron piping? Or provide a specification with minimum standards for Moore Airfield that must be met regarding fire suppression piping? It is typical for local building codes and state codes to be of a lesser standard than what a federal installation requires. The statement of work indicates in accordance state and local codes and standards only opening the door for a CVPC system to be priced. The USDA prefers the use of Schedule 40 Victaulic black iron piping. An amendment to postpone this solicitation indefinitely is posed below.

View on SAM.gov (attachments & response) ↗